Wolf Minerals' Hemerdon mine hit by equipment failures, tungsten prices, but ramp-up on schedule

"During the commissioning stage, where [mine construction contractor GR Engineering Services] was effectively trying to get tonnage throughput, there were a number of instances of equipment failures. There was wear in the second-stage crushers, basically a design flaw issue a and screw feeders feeding the material into the roaster were not working as well as they should have. ......